Project Progress Update: March 2025
- AHUH editor
- Apr 8
- 1 min read
Key Accomplishments:
✅ Site Preparation Completed
Demolition of existing structures and tree clearance finalized, establishing a clean slate for construction.
Neighboring Structure Reinforcement: Strengthened supporting piles for adjacent buildings to ensure safety during upcoming construction phases.
Southern Perimeter Wall Upgraded: Repairs and enhancements completed to guarantee long-term structural integrity and security.

✅ Sales Launch Officially Initiated
Hosted a successful sales kickoff event on March 29, 2025, signaling the official start of project marketing and client acquisition.

Next Steps (April-May 2025):🚧 Earthworks Excavation
Bulk excavation and site grading planned for mid-April, critical for foundational development.